Production Area Progress
|
Production Area - Primary Tank
2 years 6 days ago
This shows the primary fermentation tank in place. It's a 1100 liter tank - that's about 290 gallons!! On it's pallet, it stands just over Becky's head (5'5"). The chiller is in place next to it and on the left, is one of the 4 secondary tanks. |
Equipment Installation
2 years 1 week ago
The tanks have been moved in and Ben is setting up the chiller. Hoses connect the chiller to the primary fermenter to control the temperature of the must as the fermentation takes place. |
Production Area - New Floor
2 years 5 weeks ago
After much blood, sweat and tears, the Production Room floor is finally finished! 4/3/10 |
|
Production Area - Painted
2 years 11 weeks ago
Production Area with the walls painted - ready for floor epoxy and then moving in the fermentation tanks! 2/20/10 |
Production Area - Ceiling and Ducts
2 years 11 weeks ago
New duct work in and ceiling painted white. 2/14/10 |
Production Area - Primed
2 years 11 weeks ago
All primed and ready to be painted! Notice the BIG new water filter in the corner. 1/23/10 |
A timeline of pictures of the creation of the Production Area.